Terawulf earnings release, August 5, 2026

Terawulf Inc. (WULF) · Form 8-K, Item 2.02 · Filed · SEC filing

TeraWulf Reports Second Quarter 2026 Results

102 MW of revenue-generating critical IT capacity online at Lake Mariner, with an additional 336 MW under construction and delivery expected within cost and schedule guidance

Expands power-backed platform in Kentucky through ~$19 billion Anthropic lease at Justified and acquisition of the gigawatt-scale Muskie Data Campus

Agrees to monetize Abernathy Joint Venture interest for ~$530 million and reaffirms target of contracting 250–500 MW of incremental critical IT capacity annually

EASTON, Md. – August 5, 2026 – TeraWulf Inc. (Nasdaq: WULF) (“TeraWulf” or the “Company”), a vertically integrated owner, developer and operator of large-scale digital infrastructure, today announced its financial results for the second quarter ended June 30, 2026 and provided an update on its operations, development activities and strategic execution.

Second Quarter 2026 Financial Highlights

• Generated second-quarter revenue of $44.8 million, including $31.9 million of HPC lease revenue, representing approximately 71% of total revenue.

• Ended the quarter with approximately $3.0 billion of cash and restricted cash, maintaining substantial liquidity to fund contracted development and future growth.

Q2 2026 Operational and Development Highlights

• Operated 81 MW of revenue-generating critical IT capacity at Lake Mariner as of June 30, 2026 and completed delivery of CB-3 in early July, increasing revenue-generating capacity to 102 MW and satisfying the applicable conditions for $600 million of Google’s credit support for Fluidstack’s lease obligations to become effective.

• Continued construction of an additional 336 MW across CB-4 and CB-5. The first CB-4 data hall has entered commissioning, with phased delivery and rent commencement expected during the second half of 2026, while CB-5 remains targeted to begin phased delivery in early 2027. WULF Compute continues to progress within the Company’s previously disclosed cost guidance of $8-10 million per critical IT MW.

• Acquired the Muskie Data Campus in Eastern Kentucky and entered into electric service and related infrastructure agreements with Kentucky Power Company providing for up to 1 GW of contracted electric service.

Subsequent Events

• Entered into a 20-year data center lease with Anthropic for approximately 401 MW of critical IT capacity at the Justified Data Campus. The lease represents approximately $19 billion of contracted revenue over the initial term and up to approximately $33 billion if Anthropic exercises both five-year extension options.

• Entered into an agreement to sell the Company’s entire 50.1% interest in the Abernathy Joint Venture for aggregate cash consideration of approximately $530 million.

• Received FERC authorization for the proposed acquisition of the Morgantown generating station, clearing a significant regulatory condition toward closing and development of the up to 1 GW Chesapeake Data Campus.

Management Commentary

Paul Prager, Chairman and Chief Executive Officer of TeraWulf, commented:

“The second quarter demonstrates that TeraWulf is moving from platform formation to scaled execution. At Lake Mariner, we delivered additional contracted capacity and converted it into recurring lease revenue. In Kentucky, we established the next phase of growth through the Anthropic lease at Justified and the acquisition of the gigawatt-scale Muskie Data Campus.

These are not isolated developments. They reflect a repeatable model built around controlling power-advantaged infrastructure, securing long-duration customer contracts and delivering capacity in phases. As access to power becomes the defining constraint on AI infrastructure development, we believe our ability to combine energy expertise, infrastructure control and execution at scale will become increasingly valuable.

Our agreement to monetize Abernathy reflects the same discipline. We are prepared to realize value where appropriate and redeploy capital toward larger-scale opportunities where we have greater control over the infrastructure, customer relationship and long-term economics. Our objective is not simply to accumulate megawatts—it is to build a durable, capital-efficient platform that compounds value for shareholders."

Patrick Fleury, Chief Financial Officer of TeraWulf, added:

“The second quarter marked another meaningful step in the transformation of our financial profile, with HPC leasing representing approximately 71% of total revenue.

The delivery of CB-3 also unlocked $600 million of Google’s credit support for Fluidstack’s lease obligations. This is an important credit milestone that further strengthens the contracted revenue profile of the Lake Mariner buildout.

With substantial liquidity and access to project-level financing, we have the flexibility to complete our contracted developments and fund the next phase of growth. We remain focused on matching capital deployment to contracted demand and selectively recycling capital when doing so improves control, scale and long-term shareholder returns.”

Infrastructure Platform Expansion

TeraWulf continues to expand its national platform beyond its flagship Lake Mariner Data Campus, focusing on power-advantaged sites capable of supporting large-scale, phased HPC development.

Justified Data Campus - Hawesville, Kentucky

Justified is a large-scale HPC campus with access to up to approximately 480 MW of gross power capacity, an energized on-site substation, existing high-voltage transmission infrastructure and more than 250 buildable acres. Subsequent to quarter-end, TeraWulf entered into a 20-year lease with Anthropic for approximately 401 MW of critical IT capacity, with initial delivery expected in the second half of 2027 and full delivery expected in early 2028.

Muskie Data Campus - Grayson, Kentucky... (truncated)e for up to 1 GW of contracted electric service, with initial service expected in the fourth quarter of 2028 and phased development thereafter.

Chesapeake Data Campus - Morgantown, Maryland

Chesapeake is an existing grid-connected generation site with approximately 210 MW of operational capacity, substantial electrical infrastructure and significant long-term expansion potential. On July 29, 2026, FERC authorized the pending acquisition of the Morgantown generating station. Subject to the remaining closing conditions and required approvals, the site could support an integrated generation, energy-storage and data center campus capable of scaling to up to 1 GW, with initial data center operations currently contemplated for 2030.

New York Platform - Lake Mariner and Lake Hawkeye

In New York, TeraWulf continues to expand its flagship Lake Mariner Data Campus while advancing Lake Hawkeye as a longer-term redevelopment opportunity. In addition to the 102 MW of revenue-generating critical IT capacity and 336 MW currently under construction at Lake Mariner, the Company is pursuing 250 MW of incremental power capacity, subject to applicable interconnection approval. Lake Hawkeye encompasses approximately 183 leased acres at a former industrial site with existing electrical infrastructure and, subject to permitting and site development, has the potential to support approximately 400 MW of gross capacity, or approximately 320 MW of critical IT load, with operations not currently contemplated until approximately 2029.

Strategic Positioning

TeraWulf’s development model is focused on controlling power-advantaged infrastructure, securing long-duration, credit-supported customer contracts, aligning capital deployment with contracted demand and financing and delivering capacity in sequential phases. The Muskie acquisition, Anthropic lease and agreement to monetize the Company’s interest in the Abernathy Joint Venture demonstrate the repeatability of this model across site acquisition, customer contracting, project execution and capital recycling.

Against this backdrop, TeraWulf reaffirms its target of contracting 250 MW to 500 MW of incremental critical IT capacity annually. The Company intends to pursue that growth selectively, prioritizing opportunities with secured power, clear customer demand, scalable infrastructure and attractive risk-adjusted returns.

Investor Conference Call and Webcast

The Company will host its earnings conference call and webcast for the second quarter ended June 30, 2026, today, August 5, 2026, at 8:00 a.m. Eastern Time. The call will be available for replay in the “News & Events” section of the Company’s website at https://investors.terawulf.com/events-and-presentations/.

About TeraWulf

TeraWulf develops, owns and operates large-scale, power-backed digital infrastructure in the United States, purpose-built for high-performance computing and artificial intelligence workloads. The Company combines long-term control of land, power and interconnection infrastructure with deep in-house expertise in energy markets, infrastructure development and data center operations. TeraWulf operates the Lake Mariner Data Campus in New York and is developing and pursuing additional large-scale campuses in Kentucky, New York and Maryland. The Company also operates existing bitcoin-mining infrastructure at Lake Mariner, portions of which are being repurposed to support contracted HPC development.

Financial statements

Income Statement

(In thousands, except number of shares and loss per common share)

Digital asset revenue12,83547,63625,82582,041
HPC lease revenue31,93252,954
Total revenue44,76747,63678,77982,041
Costs and expenses:Cost of revenue (exclusive of depreciation shown below)12,40022,09414,76146,647
Costs and expenses:Operating expenses21,7052,03930,7213,183
Costs and expenses:Operating expenses – related party1,7331,4753,9193,223
Costs and expenses:Selling, general and administrative expenses112,4119,996240,01656,569
Costs and expenses:Selling, general and administrative expenses – related party14,5294,29214,6887,863
Costs and expenses:Depreciation21,24118,78649,71834,360
Costs and expenses:Loss (gain) on fair value of digital assets, net799-8871,452-17
Costs and expenses:Change in fair value of contingent consideration1,6001,600
Costs and expenses:Impairment of property, plant, and equipment25,697
Costs and expenses:Loss on disposals of property, plant, and equipment3993,8313993,831
Costs and expenses:Total costs and expenses185,21763,226381,371157,259
Costs and expenses:Operating loss-140,450-15,590-302,592-75,218
Costs and expenses:Interest expense-56,389-4,012-123,460-8,061
Costs and expenses:Change in fair value of warrants-755,667-971,992
Costs and expenses:Loss on extinguishment of debt-7,116-7,116
Costs and expenses:Interest income28,9561,23258,3673,491
Costs and expenses:Other income930930
Costs and expenses:Loss before income tax and equity in net loss of investee-929,736-18,370-1,345,863-79,788
Costs and expenses:Income tax provision-28-56
Costs and expenses:Equity in net loss of investee, net of tax-11,063-22,611
Costs and expenses:Net loss-940,827-18,370-1,368,530-79,788
Costs and expenses:Less: net loss attributable to noncontrolling interests-910-979
Costs and expenses:Net loss attributable to TeraWulf Inc-939,917-18,370-1,367,551-79,788
Loss per common share:Basic and diluted-1.94-0.05-3.01-0.21

Income Statement

Three Months Ended June 30, (in thousands)

Three Months Ended June 30, – 2026Three Months Ended June 30, – 2025Six Months Ended June 30, – 2026Six Months Ended June 30, – 2025
Net loss attributable to TeraWulf, Inc-939,917-18,370-1,367,551-79,788
Net loss attributable to non-controlling interest-910-979
Net loss-940,827-18,370-1,368,530-79,788
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Equity in net loss of investee, net of tax11,06322,611
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Income tax provision2856
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Other income-930-930
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Interest income-28,956-1,232-58,367-3,491
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Loss on extinguishment of debt7,1167,116
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Change in fair value of warrants755,667971,992
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Interest expense56,3894,012123,4608,061
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Loss on disposals of property, plant, and equipment3993,8313993,831
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Impairment of property, plant, and equipment25,697
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Change in fair value of contingent consideration1,6001,600
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Depreciation21,24118,78649,71834,360
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Accretion of asset retirement obligations267435
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Amortization of right-of-use asset1,8747503,7451,435
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Stock-based compensation expense83,9391,304185,35739,978
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Stock-based charitable contribution14,39014,390
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Related party expense settled with respect to common stock2,3752,375
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Acquisition-related transaction costs1,4754381,475
Adjustments to reconcile net loss to non-GAAP Adjusted EBITDA:Non-GAAP Adjusted EBITDA-18,34014,531-22,4139,836

Balance Sheet

June 30, 2026 — (In thousands, except number of shares and par value; unaudited)

June 30, 2026December 31, 2025
CURRENT ASSETS:Cash and cash equivalents2,619,1913,266,389
CURRENT ASSETS:Restricted cash142,938189,933
CURRENT ASSETS:Accounts receivable13,2021,212
CURRENT ASSETS:Digital assets133270
CURRENT ASSETS:Prepaid expenses18,3146,272
CURRENT ASSETS:Other current assets12,72614,197
CURRENT ASSETS:Total current assets2,806,5043,478,273
CURRENT ASSETS:Property, plant and equipment, net3,600,1911,507,699
CURRENT ASSETS:Equity in net assets of investee424,062446,008
CURRENT ASSETS:Goodwill55,45755,457
CURRENT ASSETS:Operating lease right-of-use asset101,754103,975
CURRENT ASSETS:Finance lease right-of-use asset117,814119,338
CURRENT ASSETS:Restricted cash266,479266,453

Balance Sheet

(In thousands, except number of shares and par value; unaudited)

Warrant liabilities1,816,690844,698
Current portion of long-term debt90,71846,316
Short-term convertible notes1,101,976489,767
Total current liabilities3,763,8711,735,848
Deferred rent liability, net of current portion94423,285
Operating lease liability, net of current portion21,22022,309
Finance lease liability, net of current portion288289
Long-term debt3,019,3353,052,240
Convertible notes1,001,0831,582,788
Deferred tax liabilities13276
Other liabilities93,994902
TOTAL LIABILITIES7,900,8676,417,737
EQUITY:Common stock, $0.001 par value, 950,000,000 authorized at June 30, 2026 and December 31, 2025; 522,901,181 and 444,534,694 issued at June 30, 2026 and December 31, 2025, respectively; 498,932,431 and 420,065,944 outstanding at June 30, 2026 and December 31, 2025, respectively523444
EQUITY:Additional paid-in capital2,656,3131,285,202
EQUITY:Treasury stock at cost, 23,968,750 and 24,468,750 at June 30, 2026 and December 31, 2025, respectively-148,309-151,509
EQUITY:Accumulated deficit-2,361,243-993,692
EQUITY:Total TeraWulf Inc. stockholders' equity147,284140,445
EQUITY:Noncontrolling interests244
EQUITY:Total equity147,528140,445
EQUITY:TOTAL LIABILITIES AND EQUITY8,048,3956,558,182

Balance Sheet

Six Months Ended June 30, — (In thousands; unaudited) (in thousands)

Six Months Ended June 30, – 2026Six Months Ended June 30, – 2025
CASH FLOWS FROM OPERATING ACTIVITIES:Net loss-1,368,530-79,788
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Amortization of debt issuance costs, commitment fees and accretion of debt discount23,0001,215
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Related party expense settled with respect to common stock2,375
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Stock-based compensation expense185,35739,978
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Stock-based charitable contribution14,390
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Depreciation49,71834,360
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Accretion of asset retirement obligations435
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Change in asset retirement obligations estimate15
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Amortization of right-of-use asset3,7451,435
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Revenue recognized from digital assets mined and hosting services-25,825-82,041
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Loss (gain) on fair value of digital assets, net1,452-17
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Change in fair value of contingent consideration1,600
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Impairment of property, plant, and equipment25,697
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Loss on disposals of property, plant, and equipment3993,831
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Change in fair value of warrants971,992
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Loss on extinguishment of debt7,116
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Deferred income tax provision56
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Other income-43
Adjustments to reconcile net loss to net cash (used in) provided by operating activities:Equity in net loss of investee, net of tax22,611
Changes in operating assets and liabilities:Increase in accounts receivable-12,123-544
Changes in operating assets and liabilities:Increase in prepaid expenses-12,042-3,259
Changes in operating assets and liabilities:Increase in other current assets-7,416-1,027
Changes in operating assets and liabilities:Decrease in deferred charges289
Changes in operating assets and liabilities:Decrease (increase) in other assets5,348-7,700
Changes in operating assets and liabilities:Increase in accounts payable5,584355
Changes in operating assets and liabilities:(Decrease) increase in accrued interest and other current liabilities-12,3941,770
Changes in operating assets and liabilities:Increase (decrease) in other amounts due to related parties464-750
Full release

Forward-Looking Statements

This press release contains forward-looking statements within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995, as amended. Such forward-looking statements include statements concerning anticipated future events and expectations that are not historical facts. All statements, other than statements of historical fact, are statements that could be deemed forward-looking statements. In addition, forward-looking statements are typically identified by words such as “plan,” “believe,” “goal,” “target,” “aim,” “expect,” “anticipate,” “intend,” “outlook,” “estimate,” “forecast,” “project,” “seek,” “continue,” “could,” “may,” “might,” “possible,” “potential,” “strategy,” “opportunity,” “predict,” “should,” “would” and other similar words and expressions, although the absence of these words or expressions does not mean that a statement is not forward-looking. Forward-looking statements are based on the current expectations and beliefs of TeraWulf’s management and are inherently subject to a number of factors, risks, uncertainties and assumptions and their potential effects. There can be no assurance that future developments will be those that have been anticipated. Actual results may vary materially from those expressed or implied by forward-looking statements based on a number of factors, risks, uncertainties and assumptions, including, among others: (1) TeraWulf’s ability to attract additional customers to lease its HPC data centers; (2) TeraWulf’s ability to complete its data center campuses and future strategic growth initiatives in a timely manner or within anticipated cost estimates; (3) operational risks associated with its data centers and TeraWulf’s ability to perform under its existing data center lease agreements; (4) changes in applicable laws, regulations and/or permits affecting TeraWulf’s operations or the industries in which it operates; (5) failure to obtain adequate financing on a timely basis and/or on acceptable terms with regard to expansion or existing operations; (6) adverse geopolitical or economic conditions, including a high inflationary environment, the implementation of new tariffs and more restrictive trade regulations; (7) the potential of cybercrime, money-laundering, malware infections and phishing and/or loss and interference as a result of equipment malfunction or break-down, physical disaster, data security breach, computer malfunction or sabotage (and the costs associated with any of the foregoing); (8) the availability and cost of power as well as electrical infrastructure equipment necessary to maintain and grow the business and operations of TeraWulf; and (9) other risks and uncertainties detailed from time to time in TeraWulf’s filings with the Securities and Exchange Commission (“SEC”). Potential investors, stockholders and other readers are cautioned not to place undue reliance on these forward-looking statements, which speak only as of the date on which they were made. TeraWulf does not assume any obligation to publicly update any forward-looking statement after it was made, whether as a result of new information, future events or otherwise, except as required by law or regulation. Investors are referred to the full discussion of risks and uncertainties associated with forward-looking statements and the discussion of risk factors contained in the Company’s filings with the SEC, which are available at www.sec.gov.

Investors

:

Investors@terawulf.com

Media

:

From SEC EDGAR. Analysis by Pear Digitals from the filing alone. Not investment advice. · Terawulf earnings · Latest earnings · Markdown

Screener

Plans

Premium and Pro coming soon.

Log in

New here?

Join the waitlist

Pear FMV opens to everyone soon. We'll email you when it does.